Setting a foundation

It’s our third day of work at the preschool in Las Minitas, where Sergio, our mason, is on his way up to begin work after Gustavo and other men (and some kids) from the community have dug a trench around the footprint and also the deep foundation holes before the holy week.
I have worked with Sergio before, in 2010, and will be glad to spend these days with him.
Soon, I’ll be there too, staying with Anunsciascion and her family and working bending rebar and mixing and pouring concrete with water we run from a hose from a sort of well down the hill.
It’s about three and a half weeks from here, folks!
The Friends Project does not mess around. :-)